Since early 2024, Arthian has supported our client, Green BESS Development Services (GBDS), on the substantial works required to facilitate the installation of a new 11-22MW (tbc) Battery Energy Storage System (BESS) adjacent to upper-tier COMAH sites. Our involvement is ongoing and includes a wide range of services relevant to our SPEN framework appointment.
The Solution
The Arthian team delivered a full scope of project work for this client, covering multiple phases from demolition to hazard reviews.
1. Demolition of Storage Tanks
Preparation of a Pre-Construction Information (PCI) package for tendering to demolition contractors, including site walkover, reconnaissance, and engineering review of existing site infrastructure.
Production of demolition drawings highlighting scope, access, and laydown requirements.
Swept path analysis for site access planning.
Detailed Demolition Scope of Works, covering:
Defined scope and extent of demolition.
Proposed construction sequence.
Client safety and site protocols.
Required documentation and contractor deliverables.
Isolation and clean-down requirements.
Coordination of site visit with demolition contractor to refine demolition strategy and outline programme.
2. New Workshop Building
RIBA Stage 1 – Preparation & Briefing
Develop and refine GBDS’s requirements with stakeholders.
Assess availability and capacity of existing utilities (drainage, power, telecoms, water).
Deliver a RIBA Stage 1 Briefing Report outlining building function and design intent.
Collate existing site data and produce PCI documentation for the new build.
RIBA Stage 2 – Concept Design
Architectural concept and layout design based on Stage 1 findings.
Development of a temporary workshop scheme.
Produce a Basis of Design report for civil and structural elements.
Civil and structural scheme design, including:
Blast-resistant structural performance.
Overhead gantry crane integration.
External works (drainage, hardstanding, road tie-ins).
Re-use of existing foundations/pile caps where feasible.
Generate scheme-level drawings and specifications.
Designer’s Risk Assessment (DRA).
Geotechnical and geoenvironmental desk studies.
3. Existing Workshop – Demolition & Modifications
RIBA Stage 1 – Preparation & Briefing
Site walkover, reconnaissance, and engineering review.
Stakeholder engagement to define demolition and modification requirements.
Review utilities and identify necessary alterations.
RIBA Stage 1 Briefing Report with scope and requirements.
PCI documentation preparation.
RIBA Stage 2 – Concept Design
Architectural concept layout for modifications.
Basis of Design report for civil and structural works.
Scheme design for required structural modifications.
Define scope for modifications to building services (fire, power, lighting, telecoms, water).
Scheme drawings, specifications, and DRA.
Supporting geotechnical/geoenvironmental studies.
4. Supplementary Scope of Works
Planning support and drawings for GIS Building and enlarged stores.
Production of Heads-of-Terms drawings, including lease areas, site/CDM boundaries.
Storage optimisation study, with moveable racking assessment.
Site inspection to verify storage and dimensions for alterations.
Order of Magnitude (OOM) cost estimate for all construction activities (+/- 50%).
Tank Inspections & Clean-Down Preparation
Structural inspection of tank access ladders.
Dip level measurements of residual volumes.
Sampling and testing of materials for cleaning scope.
Drainage Study
Review of existing arrangements and constraints.
Identification of planning considerations (climate change allowances).
Establishment of permeable/impermeable areas and runoff calculations.
Outline SuDS treatment strategy and preliminary network design.
Feasibility report with conclusions and recommendations.
The Solution
5. Site Surveys & Ground Investigation
PAS 128 Topographical and Utilities Survey for BESS site and cable route.
Ground Investigation for Cable Route and Coryton Power Station.
Principal Designer Role during tender and GI phases.
Contractor tendering, selection, and supervision.
Geotechnical Reporting
Interpretative Geotechnical Investigation Report (GIR) for new GIS Substation:
Ground and groundwater profiling.
Soil parameter derivation.
Pile recommendations.
Exploratory hole plan and cross-sections.
Risk assessment.
Technical Note on GI and pile testing for New Store Building.
Combined Geotechnical & Geo-environmental GIR for 400kV cable route:
Ground profiling and waste classification.
HDD feasibility and resistivity testing.
Cross-sections and exploratory hole plan.
Geotechnical risk assessment.
6. Geo-environmental Reporting
Phase 2 Generic Quantitative Risk Assessment (GQRA) for GIS Substation, including ground gas risk.
Waste Classification Report for Store Building.
7. COMAH Hazard Review for BESS Development
Scope of Consideration
HSE consultation zones around COMAH facilities.
Thermal radiation and fire event modelling.
Overpressure risks from pipelines.
Vulnerability assessment of infrastructure.
Cost-benefit review of mitigation measures.
Deliverables
Review of COMAH risks and hazard impacts.
Vulnerability assessment for site operatives.
Evacuation vs shelter-in-place strategies.
Fire Hazard Appraisal (FHA) for BESS site.
Recommendations for mitigation and risk reduction.