Close Close Menu

Talk to Neil Chalmers about this project

Call Me

Client:

Approach and Delivery

Our contaminated land team has been working with a client with development rights to construct an energy storage project. A spoil heap required removal off-site prior to construction works in which Arthian was instructed to collect soil samples from and prepare a waste classification report for the disposal of the spoil heap.

Project Outcomes

Arthian collected representative soil samples of the spoil heap and prepared a waste classification report in general accordance with SEPA guidance, Waste Classification: Guidance on the Classification and Assessment of Waste,WM3 V1.2GB to inform future offsite disposal routes. The key contaminants of concern were metals, TPH, PAH and asbestos. Based on a review of the soil results and HazWasteOnline reports, the waste soil material was classified for disposal to suitably licensed facilities.

To find out more about how Arthian can work with you, please get in touch.